Phase 46: Sangamon & Christian Counties

We love keeping you in the loop on our progress

Phase Progress

Planning

Right of Way

Construction

Completed

Cleanup

Phase Overview

Our Phase 46 Project in Cooper (Sangamon County) and Mount Auburn (Christian County) Townships is a water system improvement project which consists of approximately 33 miles of water main to serve approximately 107 members. The phase 46 project was awarded funding in the fall of 2018 and began construction on the project that year, however the original contractor failed to complete the project which caused a delay to finish the scope of work. In fall of 2019, MB Contractors located in Monticello, MO began construction to finish the project. All of the water mains have been installed and approximately 45 meters. The remaining meters will be installed soon with substantial project completion in the spring 2020 and cleanup scheduled for fall 2020.

Phase Updates

  • Construction is complete.

    Construction is complete. All meters are installed and members are using water. The contractor will address list this fall.

  • Approximately 40 meters have been installed and 75 are remaining.

  • All water main installed. Remaining meters to be installed shortly.